|
![]() |
|
|
Painters Creek Wetland Restoration
Project SummaryThis report is a summary of work completed to date and will be updated (see the Construction Updates section below) as additional tasks are completed. Information compiled in this report will be used to demonstrate work completed for purposes of wetland credit certification as well as to document contractor work accomplishments. There are two construction contracts for the restoration project: Both contracts are on schedule and budget. Construction ProgressVegetation ManagementSodko, the site preparation, vegetation management and revegetation contractor has been on-site throughout the spring, summer and fall. Sodko’s subcontractor, Minnesota Native Landscapes has applied herbicide, burned, mowed and disced the site. Contract work completed to date includes:
ExcavationDoboszenski started with tree clearing in December of 2000. Areas where trees were removed included the access road in the southwest corner of the site and areas where new wetland credit is to be created. Trees removed included small diameter box elder, willow and elm. Larger trees to be used for snags in the wetland were salvaged. Haul roads were plowed in the wetland with the intent to develop enough frost to support large equipment. Pond excavation is scheduled to begin in January. Following excavation work Sodko will continue vegetation management in the spring of 2001. Maintenance will continue through the fall of 2002. Construction ContractsSodko has submitted one pay request for $14,364. The remaining budget for Sodko’s contract is $104,722.00. Currently the contract is slightly under budget. Doboszenski has submitted two pay requests. One was for a materials on-hand payment for the culverts and the other for mobilization and tree clearing. Payments to date for Doboszenski total $14,077. The remaining budget for Doboszenski’s contract is $71,426.00. This contract is on budget. Construction UpdatesFebruary 2, 2001During the summer and fall of 2000, major work on invasive species control was completed though a regimen of herbicide treatment, prescribed burns, mowing and discing. These treatments had a significant positive impact with a marked increase in species diversity. In particular, the wetland, which prior to the start of the project was a reed canary monotype, exhibited a high level of native forb recruitment (joe pye weed, swamp milkweed, blue vervain and boneset) As a result, the seeding mix will be revised. Over the past month, the Excavating Contractor has been working in shallow wetland ponds removing shallow drainage ditches and scalping invasive reed canary sod from the site. They have also cut and set aside twelve large trees that will be placed at various points in the restored wetland to provide wildlife habitat structure for nesting, perching and basking. At this point, approximately 75% of excavation work is complete. It is expected that the balance of the work will be completed within the next couple of weeks. The next phase of the project will commence this spring with native tree, shrub, grass and forbs scheduled to be planted and seeded. March 1, 2001Painter's Creek Wetland Restoration: Grading is complete and we are waiting for spring (snow melt, etc.) to begin the re-vegetation phase. |